移交代維驗(yàn)收規(guī)范
深圳國人通信有限公司安徽辦事處
深圳國人通信有限公司
安徽辦事處合肥移動(dòng)工程驗(yàn)收規(guī)程
目錄
一、驗(yàn)收由建設(shè)組和代維組共同完成以下項(xiàng)目:.............................................................................1二、工程資料轉(zhuǎn)交..............................................................................................................................1三、上移動(dòng)監(jiān)控平臺(tái)..........................................................................................................................2四、安裝檢查和信號(hào)檢查..................................................................................................................2五、工程轉(zhuǎn)交...................................................................................................................................3六、附件...................................................................................................................................3
一、驗(yàn)收由建設(shè)組和代維組共同完成以下項(xiàng)目:
1、工程資料轉(zhuǎn)交
2、站點(diǎn)上移動(dòng)監(jiān)控平臺(tái)3、安裝檢查和信號(hào)檢查4、工程轉(zhuǎn)交
二、工程資料轉(zhuǎn)交
督導(dǎo)在開通申請(qǐng)得到移動(dòng)回復(fù)郵件后,轉(zhuǎn)發(fā)一份到合肥代維郵箱:grentech.hf@163.com。開通成功后,建設(shè)組一個(gè)星期內(nèi)向代維組提交站點(diǎn)資料,包括以下5項(xiàng):1、點(diǎn)位圖(見附件一)
2、最終設(shè)計(jì)方案(與實(shí)際施工相符,改動(dòng)的地方需給出設(shè)計(jì)變更單)3、開通后路測(cè)深圳國人通信有限公司安徽辦事處
4、移動(dòng)監(jiān)控平臺(tái)信息(如果沒有設(shè)備則不需要,見附件二)5、站點(diǎn)基本信息表(見附件三)
6、設(shè)備信息表(見附件四)和調(diào)測(cè)單(見附件五)
代維組在接收到站點(diǎn)資料簽開通資料交接單,在建設(shè)組和代維組負(fù)責(zé)人簽字后交工程秘書簽字存檔。站點(diǎn)資料同時(shí)轉(zhuǎn)發(fā)給商務(wù)經(jīng)理?xiàng)顜洠簓ang1611@sina.com一份。
代維組在接收資料后應(yīng)更新總的站點(diǎn)資料表,并發(fā)給市移動(dòng)綜合覆蓋班全班組。
三、上移動(dòng)監(jiān)控平臺(tái)
有主設(shè)備的站點(diǎn),工程督導(dǎo)應(yīng)在開通后及時(shí)帶蓋了章的《sim卡申請(qǐng)》到市移動(dòng)領(lǐng)取sim卡,領(lǐng)卡時(shí)需當(dāng)場(chǎng)檢查sim是否能正常收發(fā)短信。然后到現(xiàn)場(chǎng)安裝sim卡到modem中,并帶筆記本用監(jiān)控軟件和數(shù)據(jù)線(usb轉(zhuǎn)DB9公頭和DB9母頭監(jiān)控調(diào)測(cè)線)寫入短信中心+8613800551500,然后通知代維網(wǎng)管遙測(cè)。如果不通請(qǐng)檢查:1、給定的sim卡號(hào)是否正確,sim卡能否正常收發(fā)短信2、短信中心號(hào)是否設(shè)置正確
3、前端的jp7口應(yīng)該插上,在遠(yuǎn)程狀態(tài)下jp7口應(yīng)該插上與modem連接的線4、modem是否正常閃爍,如果不正常請(qǐng)嘗試按監(jiān)控板上的重啟按鈕。5、后端遙測(cè)不通時(shí)請(qǐng)檢查撥碼是否正確,撥碼設(shè)置請(qǐng)看后面詳細(xì)介紹
6、后端遙測(cè)不通時(shí),撥碼正確時(shí),請(qǐng)檢查光路損耗,如果光路損耗大于10dB或者后端光
接收小于-9dBm時(shí),前后端監(jiān)控就不能正常工作。
在自己的平臺(tái)遙測(cè)通過后,代維組監(jiān)控負(fù)責(zé)人應(yīng)在當(dāng)天或第二天到市移動(dòng)平臺(tái)上錄入調(diào)通。
四、安裝檢查和信號(hào)檢查
建設(shè)組在工程完全完工后,可以申請(qǐng)安裝檢查和信號(hào)檢查,代維組應(yīng)盡量安排在周六日去現(xiàn)場(chǎng)檢查。代維組根據(jù)轉(zhuǎn)交的工程資料,做好工程驗(yàn)收表格,會(huì)同建設(shè)組到現(xiàn)場(chǎng)檢查。安裝檢查:
1、首先檢查設(shè)備位置,設(shè)備調(diào)測(cè)參數(shù)和電表位置是否和工程資料上一致。若設(shè)備位置與工
程資料上的位置偏移樓層則
2、如果是較大的室內(nèi)分布則需抽查50%的弱電井,檢查器件連接、走線工藝和標(biāo)簽等。3、器件連接否正確和按照方案施工,如果沒有,則需要登記并要求建設(shè)組給出合理解釋。
如果因?yàn)闆]有按照方案施工而造成區(qū)域信號(hào)覆蓋弱,而且現(xiàn)場(chǎng)整改未能達(dá)到覆蓋效果,代維組可停止驗(yàn)收,要求建設(shè)組整改。再次申請(qǐng)安裝檢查和信號(hào)檢查時(shí)間往后推遲一個(gè)月。
4、若發(fā)現(xiàn)走線工藝不好,如接頭松動(dòng),防水做得不合格,線未連接,器件空載等情況,立
即停止驗(yàn)收工作,要求建設(shè)組整改,再次申請(qǐng)安裝檢查和信號(hào)檢查時(shí)間往后推遲一個(gè)月。5、用測(cè)試手機(jī)測(cè)試所有天線,包括但不限于吸頂天線、電梯內(nèi)的對(duì)數(shù)周期天線或壁掛天線、
射燈天線、路燈天線、角反射天線和草坪燈天線等。深圳國人通信有限公司安徽辦事處
1)吸頂天線,天線下一米處場(chǎng)強(qiáng)在-42dBm以上,通話上行發(fā)射功率余量應(yīng)能穩(wěn)定達(dá)
到19,通話質(zhì)量為0。
2)電梯內(nèi)的對(duì)數(shù)周期天線或壁掛天線,信號(hào)場(chǎng)強(qiáng)應(yīng)達(dá)到-75dBm以上,通話時(shí)上行發(fā)
射功率余量應(yīng)穩(wěn)定達(dá)到7以上,平均值應(yīng)能達(dá)到10,通話質(zhì)量0。
3)射燈天線,天線下30米處應(yīng)該能達(dá)到-40dBm以上,通話上行發(fā)射功率余量應(yīng)能穩(wěn)
定達(dá)到19,通話質(zhì)量為0。
4)路燈天線,天線10米外場(chǎng)強(qiáng)在-40dBm以上,通話上行發(fā)射功率余量應(yīng)能穩(wěn)定達(dá)到
19,通話質(zhì)量為0。
5)角反射天線,天線下30米處場(chǎng)強(qiáng)-35dBm以上,通話上行發(fā)射功率余量應(yīng)能穩(wěn)定達(dá)
到19,通話質(zhì)量為0。
6)草坪燈天線,天線10米外場(chǎng)強(qiáng)在-42dBm以上,通話上行發(fā)射功率余量應(yīng)能穩(wěn)定達(dá)
到19,通話質(zhì)量為0。
7)若有少量天線(吸頂天線總數(shù)不超過3面,其他天線不超過1面)可以允許建設(shè)組
立即整改,三天內(nèi)完成再到現(xiàn)場(chǎng)復(fù)測(cè)良好,則信號(hào)測(cè)試通過。超過以上的認(rèn)定天線不合格,則停止驗(yàn)收,要求建設(shè)組整改,再次申請(qǐng)安裝檢查和信號(hào)檢查時(shí)間往后推遲一個(gè)月。
五、工程轉(zhuǎn)交
工程資料轉(zhuǎn)交、上移動(dòng)監(jiān)控平臺(tái)、安裝檢查和信號(hào)檢查等步驟通過后,由建設(shè)組現(xiàn)場(chǎng)督導(dǎo)和代維組現(xiàn)場(chǎng)工程人員在工程交維接收單上簽字,并分別交給建設(shè)組負(fù)責(zé)人和代維組負(fù)責(zé)人簽字后交給工程秘書簽字存檔,工程項(xiàng)目進(jìn)入維護(hù)階段。
六、附件
附件一,點(diǎn)位圖
C:\\Users\\ysj\\Desktop\\綠園小區(qū).doc
附件二,上監(jiān)控平臺(tái)申請(qǐng)表
C:\\Users\\ysj\\Desktop\\申請(qǐng)上移動(dòng)監(jiān)
附件三,站點(diǎn)基本信息表
C:\\Users\\ysj\\Desktop\\綜合覆蓋系統(tǒng)深圳國人通信有限公司安徽辦事處
附件四,設(shè)備信息表
C:\\Users\\ysj\\Desktop\\設(shè)備資料模板
附件五,設(shè)備調(diào)測(cè)單模版
附件六,sim卡申請(qǐng)單
C:\\Users\\ysj\\Desktop\\國人公司sim
附件七,開通資料交接單
C:\\Users\\ysj\\Desktop\\開通資料轉(zhuǎn)交
附件八,工程交維接收單
C:\\Users\\ysj\\Desktop\\工程交維接收
擴(kuò)展閱讀:集團(tuán)專線工程移交與驗(yàn)收規(guī)范vv1
集團(tuán)專線工程移交與驗(yàn)收規(guī)范
集團(tuán)專線工程移交與驗(yàn)收規(guī)范
中國移動(dòng)通信集團(tuán)廣東公司深圳分公司
網(wǎng)絡(luò)維護(hù)中心傳送室
201*年3月
第1頁共9頁集團(tuán)專線工程移交與驗(yàn)收規(guī)范
聲明
本文檔所有權(quán)和解釋權(quán)歸中國移動(dòng)廣東公司所有,未經(jīng)書面許可,不得復(fù)制或向第三方公開。
ThisdocumentisthepropertyofCMCCGDandcanbeneitherreproducednordisclosed
toathirdpartywithoutawrittenauthorization.
修訂歷史記錄
版本1.01.1日期201*-12-28201*-3-3AMDAM修訂者胡瓊趙巖起草修改說明(A-添加,M-修改,D-刪除)
第2頁共9頁集團(tuán)專線工程移交與驗(yàn)收規(guī)范
目錄
1前言...........................................................................................................................................41.1編寫目的.......................................................................................................................41.2適用對(duì)象與范圍...........................................................................................................42驗(yàn)收流程與準(zhǔn)備工作...............................................................................................................4
2.1基本驗(yàn)收流程...............................................................................................................42.2驗(yàn)收前準(zhǔn)備工作...........................................................................................................52.3驗(yàn)收內(nèi)容.......................................................................................................................62.4驗(yàn)收分工.......................................................................................................................63現(xiàn)場(chǎng)驗(yàn)收...................................................................................................................................63.1資料核對(duì)....................................................................................................................................6
3.2電源及接地...................................................................................................................63.3工藝檢查.......................................................................................................................73.4性能測(cè)試.......................................................................................................................73.5倒換測(cè)試.......................................................................................................................73.6光纜管道驗(yàn)收...............................................................................................................84網(wǎng)管驗(yàn)收...................................................................................................................................8
4.1資料核對(duì).......................................................................................................................84.2數(shù)據(jù)配置規(guī)范性...........................................................................................................85資產(chǎn)驗(yàn)收...................................................................................................................................86遺留問題...................................................................................................................................8
第3頁共9頁集團(tuán)專線工程移交與驗(yàn)收規(guī)范
1前言
1.1
編寫目的
本文主要規(guī)范新增、調(diào)整集團(tuán)專線從工程建設(shè)到網(wǎng)維維護(hù)移交的相關(guān)流程。
1.2適用對(duì)象與范圍
本手冊(cè)適用對(duì)象為深圳移動(dòng)面向集團(tuán)客戶服務(wù)支撐的網(wǎng)絡(luò)管理與維護(hù)人員,以及深圳移動(dòng)合作單位的代維工作人員。
2驗(yàn)收流程與準(zhǔn)備工作
2.1
基本驗(yàn)收流程
驗(yàn)收基本流程參照以下流程圖執(zhí)行。
第4頁共9頁集團(tuán)專線工程移交與驗(yàn)收規(guī)范
開始形成文件《專線資料移交表(光纜+設(shè)備)》光纜圖紙工程傳輸驗(yàn)收前一天14:00提交驗(yàn)收資料(郵件+支撐系統(tǒng)+管線系統(tǒng))專線建設(shè)完成3天后,未上業(yè)務(wù)前提交驗(yàn)收,網(wǎng)維傳輸網(wǎng)絡(luò)支撐組代維各接口人安排各公司驗(yàn)收(設(shè)備+光纜)支撐組代維需確認(rèn)支撐系統(tǒng)及管線系統(tǒng)資料的準(zhǔn)確性否維護(hù)組于驗(yàn)收次日反饋專線點(diǎn)涉及光纜情況維護(hù)組確認(rèn)光纜是否接手維護(hù)《專線驗(yàn)收反饋表(光纜)》是支撐組于周五前匯總整體驗(yàn)收情況《駐地網(wǎng)專線驗(yàn)收匯總表》情況1維護(hù)組確認(rèn)設(shè)備是否接手維護(hù)情況2退回整改接手維護(hù)網(wǎng)維傳輸支撐組代維在支撐在線系統(tǒng)確認(rèn)驗(yàn)收結(jié)果是集團(tuán)客戶支撐管理系統(tǒng)-專線驗(yàn)收模塊系統(tǒng)登入方式::8082/logintest.aspx否工程管理中心:傳輸室安排施工隊(duì)整改,并以照片形式反饋是網(wǎng)絡(luò)維護(hù)中心:傳輸室以月度為單位簽署補(bǔ)充協(xié)議結(jié)束
2.2驗(yàn)收前準(zhǔn)備工作
集團(tuán)專線驗(yàn)收需要滿足如下前提才可進(jìn)行驗(yàn)收工作:1、工程調(diào)測(cè)通過;
2、客戶機(jī)房現(xiàn)場(chǎng)滿足驗(yàn)收條件,如布線、標(biāo)簽、電氣等,具體請(qǐng)參考本規(guī)范。3、與客戶約定驗(yàn)收時(shí)間;
第5頁共9頁集團(tuán)專線工程移交與驗(yàn)收規(guī)范
4、與各部門及專業(yè)室、代維人員約定時(shí)間。
5、移交資料(專線資料移交表、光纜圖紙)已齊備且與設(shè)計(jì)一致,而且專線資料已錄
入支撐系統(tǒng),新增和割接光纜管道的圖紙已錄入管線系統(tǒng)。6、新增設(shè)備已上網(wǎng)管。
2.3驗(yàn)收內(nèi)容
集團(tuán)專線驗(yàn)收分為現(xiàn)場(chǎng)驗(yàn)收和網(wǎng)管驗(yàn)收兩部分,F(xiàn)場(chǎng)驗(yàn)收包括資料核對(duì),電源及接地,施工工藝,倒換測(cè)試,光纜管道驗(yàn)收。網(wǎng)管驗(yàn)收包括資料核對(duì)和數(shù)據(jù)規(guī)范性檢查。
2.4驗(yàn)收分工
機(jī)線一體化代維負(fù)責(zé)新建光纜管道的驗(yàn)收工作和集團(tuán)專線電路匯聚層以上部分的設(shè)備驗(yàn)收工作,主要是機(jī)樓內(nèi)新增設(shè)備、線纜。專線電路代維負(fù)責(zé)集團(tuán)專線電路匯聚層以下部分的設(shè)備驗(yàn)收工作(包括網(wǎng)管數(shù)據(jù)),主要是基站和客戶機(jī)房內(nèi)新增設(shè)備、布放線纜、新建接入環(huán)的驗(yàn)收工作。
3現(xiàn)場(chǎng)驗(yàn)收3.1資料核對(duì)
機(jī)線一體化代維檢查機(jī)樓內(nèi)新增設(shè)備類型和數(shù)量、業(yè)務(wù)架位、纖纜連接是否與資料一致。專線電路代維檢查基站、客戶機(jī)房內(nèi)新增設(shè)備類型和數(shù)量、組環(huán)情況、纖芯路由與移交資料是否相符。
3.2電源及接地
1、接入環(huán)局端和機(jī)樓內(nèi)新增設(shè)備要接上雙電源,要接地。
2、基站內(nèi)新增設(shè)備、客戶機(jī)房內(nèi)新增設(shè)備至少與客戶設(shè)備具備相同的供電條件;、
客戶機(jī)房如果有DC架或者UPS和條件下,不允許出現(xiàn)設(shè)備直接接市電的情況?蛻魴C(jī)房條件不滿足可以接市電;緝(nèi)DC架滿或者需要增加開關(guān)的,需要工程跟動(dòng)力室協(xié)商擴(kuò)容或者割接。
3、基站內(nèi)新增設(shè)備、客戶機(jī)房內(nèi)新增設(shè)備至少要與客戶設(shè)備具備相同的接地條件,具
備接地條件的要接地。
第6頁共9頁集團(tuán)專線工程移交與驗(yàn)收規(guī)范
3.3工藝檢查
1、具備條件的機(jī)房必須要安裝綜合機(jī)柜,綜合機(jī)柜并必安裝牢靠并且配備DDF架;
設(shè)備引出2M線必須在DDF架成端。如新增設(shè)備或新增電路在現(xiàn)有DDF架已用滿的情況下,必須增加DDF架。
2、設(shè)備安裝牢靠,安裝位置要利于換板及放線。
3、尾纖和線纜布放整齊美觀;尾纖引出尾纖槽部分必須使用保護(hù)套管;必須按現(xiàn)場(chǎng)情
況選擇適當(dāng)長度的尾纖進(jìn)行布放,避免出現(xiàn)大部分尾纖盤放在ODF上方或內(nèi)部的情況;信號(hào)電纜與電源線分開布放且沿綜合機(jī)柜側(cè)邊捆扎走線,扎帶剪切口平滑;機(jī)架頂防蟲網(wǎng)剪切合理;尾纖、信號(hào)線纜、電源電纜等連接牢固。
4、標(biāo)簽格式清晰且粘貼規(guī)范。具體標(biāo)簽格式見附件。另外對(duì)標(biāo)簽粘貼要求如下:
1)設(shè)備點(diǎn)標(biāo)簽必須為打印,跳纖點(diǎn)標(biāo)簽如果出現(xiàn)纖芯更改,可以在打印標(biāo)簽上手
寫修改。
2)電路在轉(zhuǎn)接點(diǎn)(如綜合合機(jī)柜DDF架和業(yè)務(wù)設(shè)備DDF/UTP架)必須有清晰標(biāo)簽,
標(biāo)簽的內(nèi)容包括電路名稱(以調(diào)單電路名稱為準(zhǔn))、本端信息、對(duì)端信息。
3.4性能測(cè)試
在上業(yè)務(wù)前,必須進(jìn)行離線業(yè)務(wù)測(cè)試。E1電路至少掛表15分鐘,要求無誤碼。以太網(wǎng)業(yè)務(wù)測(cè)試帶寬達(dá)到90%以上。對(duì)于裸纖專線,一定要求提供兩側(cè)光模塊參數(shù)、實(shí)際收光功率及整個(gè)纖芯路由的OTDR曲線。
3.5倒換測(cè)試
倒換測(cè)試主要針對(duì)是新建接入環(huán),對(duì)于單個(gè)站點(diǎn)新增設(shè)備可省去此部分。
新建的接入環(huán)到匯聚層采用的是1+1線形復(fù)用段保護(hù)(MSP),所以驗(yàn)收時(shí)一定要測(cè)試MSP保護(hù)倒換的功能。驗(yàn)收時(shí)需要網(wǎng)管配合完成,測(cè)試方法嚴(yán)格遵照以下的方法:
以驗(yàn)收布吉一C(1)環(huán)為例,選擇該環(huán)中一個(gè)站點(diǎn)(布吉廣場(chǎng)L),將誤碼儀掛在一條2M電路上,在交換端(龍崗機(jī)房)向基站環(huán)回(由網(wǎng)管上環(huán)回),此時(shí)誤碼儀顯示2M通路正常。
1、在布吉廣場(chǎng)L處斷開PP環(huán)的主環(huán)方向尾纖,倒換后誤碼儀沒有誤碼,斷纖兩側(cè)出
RLOS告警,同時(shí)有PS告警(metro1000還會(huì)有TU-AIS告警,metro500無)。2、保持步驟1的斷纖狀態(tài),聯(lián)系網(wǎng)管關(guān)閉布吉一C(1)到匯聚層的MSP工作通道激
第7頁共9頁集團(tuán)專線工程移交與驗(yàn)收規(guī)范
光器,觀察誤碼儀,倒換后沒有誤碼產(chǎn)生,對(duì)應(yīng)光口RLOS告警,同時(shí)有APS及APS_INDI告警。
完成以上兩個(gè)步驟后,倒換測(cè)試的驗(yàn)收完成。
注1:如果對(duì)應(yīng)匯聚層設(shè)備有下地電口,測(cè)試電路可以從該設(shè)備一個(gè)電口做到基站,這樣也可以在基站端口打環(huán),在匯聚層的下地電口進(jìn)行掛表。
注2:如果新增設(shè)備已有業(yè)務(wù),可以通過檢查業(yè)務(wù)是否正常,同時(shí)開啟新環(huán)所有接入節(jié)點(diǎn)的15分鐘性能監(jiān)測(cè),檢查是否有異常性能事件,來確定倒換是否正常。
3.6光纜管道驗(yàn)收
集團(tuán)專線光纜管道驗(yàn)收規(guī)范參見《光纜管道驗(yàn)收規(guī)范》。
4網(wǎng)管驗(yàn)收
4.1
資料核對(duì)
對(duì)照移交資料,檢查設(shè)備名稱和數(shù)量、網(wǎng)元IP、網(wǎng)元ID、網(wǎng)絡(luò)拓?fù)、網(wǎng)元間纖纜連接、單板配置是否與移交資料相符合。
4.2數(shù)據(jù)配置規(guī)范性
網(wǎng)管無告警。檢查邏輯系統(tǒng)、保護(hù)配置、時(shí)鐘設(shè)置是否正確,性能監(jiān)測(cè)是否打開,主機(jī)軟件版本是否滿足要求(metro100043SCB版本要求4.02.06.41P06以上)。具體參考《網(wǎng)管數(shù)據(jù)檢查標(biāo)準(zhǔn).doc》
5資產(chǎn)驗(yàn)收
根據(jù)工程提供的資產(chǎn)明細(xì)表,檢查資產(chǎn)標(biāo)簽、實(shí)物標(biāo)簽、實(shí)物是否一致。資產(chǎn)驗(yàn)收由于涉及到向財(cái)務(wù)上報(bào)以及打印資產(chǎn)標(biāo)簽等流程,不在首次集團(tuán)專線工程移交與驗(yàn)收范圍內(nèi),需要后期分批,與工程協(xié)商辦理資產(chǎn)移交手續(xù)。
6遺留問題
對(duì)于集團(tuán)專線工程移交與驗(yàn)收過程中出現(xiàn)的遺留問題,現(xiàn)場(chǎng)記錄下來及反饋相關(guān)負(fù)責(zé)部門或?qū)I(yè)室。由網(wǎng)服中心協(xié)調(diào)各部門及室,進(jìn)行后期的遺留問題解決工作,如屬工程遺留問
第8頁共9頁集團(tuán)專線工程移交與驗(yàn)收規(guī)范
題,由工程負(fù)責(zé)完成解決。遺留問題記錄模板參見《附件:工程驗(yàn)收遺留問題跟蹤記錄表》
第9頁共9頁